CRIAD
For Owners and operatorsData centre delivery · 7 use cases

Time-to-power is the race. Waiting on answers is the drag.

Hyperscale, colocation or enterprise, the pattern is the same. Schedules rarely stall on concrete. They stall on decisions: submittals, change assessments and RFIs waiting on information held in different systems. With Criad the answer and its evidence are in the meeting. Meetings with decisions, not a plan for more meetings.

The cost of waiting

Where the time goes

Every day a hall waits to energise is a day of lost revenue. Most of those days are not spent building. They are spent waiting: a submittal sits, a change assessment goes round several companies, an RFI makes its round trip. You pay for the wait on every site, and the same questions come back on the next one.

TODAYENERGISE
1
2
3
  • 1submittal sits
  • 2change assessment
  • 3RFI round-trip
ON CRIADENERGISE
time recovered

answers come with evidence; decided in the meeting

buildingwaiting on answersschematic, not to scale

The cost of waiting

$8-40M

per day · per gigawatt

Lost revenue for every day a gigawatt of capacity waits to energise.

Low end: colocation-rate delay estimates (Exto, 2026) · top: AI capacity pricing, ~$15M per MW-year (2025 analyses)

$720-745B77%

Planned 2026 capital spend by the four largest cloud builders, most of it AI data centres. Up 77% on 2025.

Source: company Q2 2026 earnings guidance.

What we hear most

Four issues, in your words.

01

The progress report says on track. Nobody can show which elements that is based on.

02

We asked for a change to the cooling units on one page. The knock-ons arrived later, as claims.

03

Every campus repeats the last one, and every project team checks it again by hand.

04

Handover is a pile of files. Operations starts by rebuilding the record.

Use case

Your standards, checked on every design issue

We have a design standard. Finding out whether this project follows it takes a review team and a month.

Early design runs several options in parallel, and a technology change can land mid-design. Load your standard, your basis of design or an open specification beside the project documents. Criad checks each option and each design issue against it, element by element, and lists the departures with the clause and the measurement, so your reviewers spend their time on the judgement calls.

Open this use case

Owner standard against product data · rack envelope

governs
PDFRack specificationpage 42 of 118

Envelope clause

Racks shall fit the envelope

0.60 × 1.20 × 2.00 m (W × D × H)

at every position shown on the layout.

42 of 118

Ranked by authority

Positions checked on the model

240 of 240 fail on height

PDFOpen Rack V3 base specificationpage 3 of 12

Public specification, rev 1.1

Width 600 mm · depth 1,068 mm

Height 2,286 mm

Load rating 1,400 kg

3 of 12

Width and depth fit. The 2.286 m height exceeds the 2.00 m envelope at every position. Departure listed for the designers.
Use case

Densify within the footprint

We have to double the capacity of this site in the same footprint, without doubling the capex.

Higher-density racks and a move from air to hybrid or liquid cooling change three things at once: the load on the slab, the clearances around every unit and the draw on every feed. Criad checks a proposed option against the model and the governing documents, hall by hall, so the feasibility answer comes with its evidence and the structural questions are named before the design moves.

Open this use case
Hall 2 · DH_02 Hall 2 · 240 rack positions
Highlighted: the elements the answer refers to
Use case

Progress you can audit

The monthly report says the hall is on track. Nobody can show which elements that is based on.

Install status per element rolls up from the model, not from retyped returns. The same check renders as exec tiles, a spreadsheet, a sentence or a 3D view, and every number is cited.

Open this use case
Dashboard
0 / 0
HALL 2 CABINETS INSTALLED
A4401
WORK PACKAGE
Day 0
REPORT DATE

The same check as exec tiles, every number cited.

Excel
ELEMENT
PACKAGE
STATUS
Cabinet H2-001
A4401
Not started
Cabinet H2-002
A4401
Not started
Cabinet H2-003
A4401
Not started
16 of 16 pending
package A4401

The same rows, straight into the spreadsheet teams already use.

Plain text

"Which Hall 2 cabinets are installed?"

source: Progress layer · package A4401

The same answer as a sentence, citation included.

3D view · the real model
Hall 2 power cabinets isolated on the model
Hall 2 · Power · 16 cabinets

The same 16 cabinets, isolated on the real model in the product.

Four renderings, one source. Because they all draw from the same connected data, they can never disagree with each other.
Use case

Check once, repeat on every site

Every campus repeats the last one. Every project team still checks it again by hand.

Your campuses repeat: your project knowledge should too. Every element is linked to its drawing, spec, order and status, so a check written on one site re-runs on the next.

Open this use case

SITE 1 · STRUCTURED

HALL 1✓
HALL 2✓
HALL 3✓
HALL 4✓
  1. 1Ingest as issued: model, 152 sheets, specs
  2. 2Link: element → drawing · spec · order · status
  3. 3Verify: by authority, measured on geometry

One campus, fully structured

SITE 2

same checks · re-run ✓

SITE 3

same checks · re-run ✓

SITE N

same checks · re-run ✓

Knowledge compounds across the fleet

OPERATIONS · FROM DAY ONE

> which rack is this?

✓ schedule row, spec, approvals attached

> what serves it?

✓ rack ← distribution frame ← fibre entry

> still under warranty?

✓ O&M row and warranty on record

The record stays live and queryable for decades

example queries from a structured reference campus

Use case

Approve a change with every knock-on in view

We asked for a change to the cooling units on one page. The knock-ons arrived later, as claims.

One change is never one change. Before you approve it, see what it touches: the product order, the governing drawing, the install plan. The evidence is in front of the person who decides.

Open this use case
Mechanical yard Mechanical yard · the plant behind the change
Highlighted: the elements the answer refers to
Use case

Commissioning readiness

Commissioning slipped by weeks. A clearance nobody spotted, a section left out, a permit that took a fortnight.

Commissioning is where every unresolved question surfaces at once. Criad keeps each system's install status, its outstanding clearances and the access it needs in one record, so the commissioning team can see what is ready, what is blocked and what each block is waiting on, before the commissioners are booked.

Open this use case
Hall 2 · DH_02 Hall 2 · package A4401 and the fire system
Highlighted: the elements the answer refers to
Use case

A handover record that operates

Handover is a pile of files. Operations starts by rebuilding the record.

The handover is the links, kept alive. Each element keeps its O&M row, its warranty and its power and fibre paths, so the record stays live and queryable for decades.

Open this use case

42U RACK · DATA HALL

  • 0.60 × 1.20 × 2.00 m
  • 240 per hall
  • 1 of 1,440 on campus
  • measured in

    3D MODEL

    Real geometry, shared origin: sizes and

    clearances are measured, never guessed

  • drawn on

    GOVERNING DRAWING

    telecom layout · rev 1 · issued 17 Jul 2026

    a new revision updates every element on it

  • limited by

    SPEC CLAUSE

    envelope max 0.60 × 1.20 × 2.00 m · telecom spec

    ✓ checked automatically, every revision

  • ordered as

    PRODUCT & ORDER

    one approved product · 1,440 units

    approve once, the whole order updates

  • built under

    PROGRESS

    status per rack · phase-aware, both phases

    reports roll up live, nothing retyped

  • operated as

    OPERATIONS

    O&M row · warranty · fibre & power paths

    the handover is these links, kept alive

real values from a structured reference campus

The ask

Judge it on a real job.

Book a call. Bring a real question from a job you know, and see how the answer and its evidence come together.

Your project, as it is. Drawings, specs, model and programme come in without retyping.

Your questions, with evidence. Every answer cites the sheet, the clause or the measurement.

Your people decide. Every decision keeps its evidence for later review.

Stop waiting. Start building.

Book a call with the founders. Thirty minutes, your questions, and what Criad looks like on a data centre build.

Book a call